Cable slide 3D wiring model

BAL Exact-Slide (XACT)

A BAL Exact-Slide (XACT) has a motor at the top of each jamb. Its chain pulls Out cables to the room's inside end and In cables to its outside end, and the eMFORCE control shuts each motor off when its side seals.

Parts in this model

The sequence

  1. At rest. The room is in. The outside (In) cables hold it against the wall; the control sleeps after 5 minutes without a switch input.
  2. Extend. SW OUT gets 12 V. The control runs both motors; each chain takes up its jamb's inside cables and pays out the outside ones, pulling the room's inner end toward the wall.
  3. Full out. The inside standoffs reach the wall and the control turns each motor off. Keep holding the switch until both stop: that's the best seal.
  4. Retract. SW IN gets 12 V. Both motors reverse; the outside cables pull the room's outer end back to the wall and the control shuts each motor off as it seals.

Faults you can find with the meter

Numbers

Keep going on slides and leveling

Learn it

Prove it

See it in 3D

Codes and specs

On the job